Timetable
EEDA's bidding process will be run in two stages, initially
requiring submission of an Expression of Interest (EoI) and
finally submission of a full Local Development Strategy.
- 19 September 2007 - Launch of LEADER prospectus
September by EEDA
- 15 October - Greensand Ridge Open Meeting
- 16 October-early November - work on first draft of EoI
- w/c 12 November - first meeting of prospective Greensand
Ridge Local Action Group
- Further work on draft EoI
- 10 December - EEDA deadline to receive our EoI
- w/c 14th January 2008 - Feedback from EEDA on EoI
- w/c 18th and
25th February - consultation evenings, thematic groups
- 3 March - further meeting of prospective Greensand
Ridge Local Action Group
- 14th March 2008 - EEDA deadline for receipt of our
full application and Local Development Strategy
- w/c 5th May 2008 - Notification from EEDA of outcome of
bidding round